General area is marked by ashram residents so the grass can be removed.

Grass is mowed REALLY short by ashram residents.

Construction workers measure and mark the exact area.

Construction workers build the concrete forms.

Plumbing stub-ups are complete.

Electrical conduit is put in place

Concrete is poured

Concrete finishing

Framing begins

Framing is complete, ready for siding and roof

Roof and siding complete, electrical service installed

And now we switch to photos of the inside progress…

Plumbing and electrical complete

Insulation installed

Drywall installed

Septic tank installed

Taped and floated, ready for texture and paint

Trim, cabinets and doors installed

Walls and ceilings textured; walls, ceilings, doors, and trim painted

Formica counter tops installed

Tile flooring is nearly complete

Finished laundry room with two donated washing machines

Bathroom vanity with three sinks; the mirror remains to be installed

Four showers with dressing areas (left), three toilet stalls (right)